The complexity of the Banner implementation requires a phased rollout
of systems and modules over the 24-month life of the project. Here are
key milestones to watch for. More detail about each will be posted as
each milestone date gets nearer:
 |
M1 |
Project Planning Begins |
February 2006 |
 |
M2 |
Project Definition Approved |
May 2006 |
 |
M3 |
Project Kick-Off |
June 1, 2006 |
 |
M4 |
Banner & Oracle Test Environment Installation |
August 2006 |
 |
M5 |
Luminis Portal Deployed |
January 2007 |
 |
M6 |
Banner Finance Deployed |
June 2007 |
 |
M7 |
Banner Human Resources Deployed
(payroll and web time entry) |
January 2008 |
| |
M8 |
Banner Student Admissions/Recruiting for Fall
of 2008 |
August 2007 |
 |
M9 |
Banner Financial Aid for Packaging Fall of 2008 |
March 2008 |
| |
M10 |
FAMIS Facilities Management System |
January 2008 |
| |
M11 |
Banner Student Registration for Fall of 2008
(with Degree Audit) |
June 2008 |
| |
M12 |
DegreeWorks Deployed |
Spring 2008 |
| |
M13 |
Enterprise Data Warehouse |
TBD |
| |
M14 |
Project Complete |
December 2008 |