FUTURE WORK Now that a system for construction has been developed, further steps can be taken to bring the House of the Future from concept to reality. As technology progresses, new techniques, products, and materials will become available. These can be integrated into the design to meet the demands of an ever-changing climate and ever-growing populations. Advances in energy efficiency, material reuse, and safety precautions can be implemented and concepts reworked to offer "greener" habitats that coexist less disruptively with their natural surroundings, or safer and more comfortable homes for people in all regions of the world. Additionally, after a substantial initial investment for fabrication facilities and other components of a production infrastructure, costs of manufacturing and assembly will drop rapidly, permitting for rapid mass-production of House of the Future-type structures and thus next-generation houses that are not only safer, more efficient, and more flexible, but less expensive as well. First and
foremost, however, the structure must be built. Because this project
has seen a methodological approach come from its efforts, the next logical
step is to take that approach and craft it into a tangible product:
erect the House and bring the future into today. IPRO Challenges There were a number of aspects of this IPRO that might have been tended to more effectively than they were. Unfortunately, these problems were not identified sufficiently early on in the course of the project, and the IPRO 301 team was left with little time in which to rectify them. What can be done, however, is the documentation and analysis of these logistical and organizational problems so that future IPRO teams may avoid them altogether or, failing such avoidance, remedy them while there is ample time remaining in the project. Project
Goal and Objective Dynamics of Subteams This IPRO team was organized into three smaller subteams. The subteams acted as specialized task forces dedicated to in-depth research on the various aspects of constructing the House. Subteams were defined for researching and developing the core system of design for the House, integrating new technologies into the House to support its functions, and researching building codes, safety concerns, and human-needs considerations by which the other subteams would be guided. The problem the three subteams encountered was that of redundancy in the work addressed by each subteam. There were times during which two teams would be focusing on the same topic without knowing and without communicating to each other that such overlap had been occurring. This reinforces the need for clearly-defined goals to be established as early as is practically possible in the course of the project. Valuable time could have been reclaimed had the subteams been given clear boundaries within which to conduct their research and development. Additionally, the IPRO 301 team divided itself into these specialized subteams too early on in the project. While it is important to establish guidelines for subteams as early as possible, this is not to say that the division itself should occur next to immediately. Had the IPRO 301 team taken more time at the outset of the project to plan overall team objectives, establishing subteam objectives and guidelines would have been made considerably less complex. Finally, the distribution of team members into subteams was grossly uneven. The largest subteam, dedicated to developing the core system of design and construction, consisted of seven members with an overall concentration in architectural specialists. The team dedicated to researching and implementing next-generation technologies consisted of four members. The team dedicated to researching regulations, code, and health and safety concerns consisted of only two members. A redistribution of human resources would have yielded not only the benefit of more evenly distributed workloads, but also a less homogeneous design team and more representation of architectural practices and tendencies in those subteams whose focus was not primarily architectural in nature. Communication Time With regard to a
project timeline, contingency time for deadlines and delivery dates
is paramount. By allowing for a week or more of flex time by way of
creating "virtual deadlines" an IPRO team can give itself much-needed
breathing room make last-minute revisions or updates to project deliverables,
and to communicate concerns about those objectives or deliverables amongst
its members before the time comes to submit materials to the project's
administration. |